## Revise a production-support schedule after a dependency changes

Fictional coordination exercise for a small interview project. This is not a complete production or safety plan, and it contains no real participant contact details.

### Original interview schedule

| Task | Time | Dependency |
| --- | --- | --- |
| Room access and setup | 09:00–09:30 | Permission confirmed |
| Playback and equipment checks | 09:30–10:00 | Setup complete |
| Interview | 10:00–10:45 | Interviewee and crew ready |
| File handoff and review | 10:45–11:15 | Interview recording complete |
| Room booking ends | 11:30 | Cannot assume an extension |

## Your turn

The interviewee can arrive only at 10:30. What changes, who must be informed and which assumption must not be made silently?

## Your answer

[Write your approach here.]

## For your own application

Include one change log and one concise update message in your coordination portfolio. Keep approved, pending and completed states separate.